How long does planning permission last
Before 1968, there was no limit on the duration of planning permissions. Between 1968 and 2009, the duration of a permission was generally set out in the conditions to the permission, often limited to 5 years within which time construction had to begin, although it was sometimes possible to extend this by applying to vary the condition.
However, since 2009, unless the permission states otherwise, development should begin within 3 years of the date permission was granted.
The development is considered to have begun ‘…on the earliest date that a "material operation" in connection with the development is started’, that is:
- Any work of construction in the course of the erection of a building.
- Any work of demolition of a building.
- The digging of a trench which is to contain the foundations, or part of the foundations, of a building.
- The laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned (above).
- Any operation in the course of laying out or constructing a road or part of a road.
- Any change in the use of any land which constitutes material development.
Ref Town and Country Planning Act 1990, Section 56.
Lawfully commencing the development works may first involve satisfying conditions applied to the permission.
If the development has not commenced within three years, the permission will be considered to have expired, and if the applicant still wishes to proceed with the development, they will need to renew the application. Renewal is generally less onerous than making a fresh application, but a fee is payable. If however, the conditions under which the original permission was granted have changed, it may be necessary to make a fresh application.
Once the development has commenced, the permission remains in place unless the local authority serves a completion notice. If such a notice is served, the development must then be completed within 12 months.
If an outline planning application has been made, then the relevant reserved matters applications must be made within three years. The permission will then last for a further 2 years.
See also: How long does it take to get planning permission.
[edit] Related articles on Designing Buildings
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Community Infrastructure Levy.
- Design and access statements.
- Detailed planning application.
- Environmental impact assessment.
- Extensions to time limits for implementing existing planning permissions.
- How long does it take to get planning permission.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- The difference between planning permission building regulations approval.
Featured articles and news
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.
Reslating an ancient water mill
A rare opportunity to record, study and repair early vernacular roofs.
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.























Comments