How long does planning permission last
Before 1968, there was no limit on the duration of planning permissions. Between 1968 and 2009, the duration of a permission was generally set out in the conditions to the permission, often limited to 5 years within which time construction had to begin, although it was sometimes possible to extend this by applying to vary the condition.
However, since 2009, unless the permission states otherwise, development should begin within 3 years of the date permission was granted.
The development is considered to have begun ‘…on the earliest date that a "material operation" in connection with the development is started’, that is:
- Any work of construction in the course of the erection of a building.
- Any work of demolition of a building.
- The digging of a trench which is to contain the foundations, or part of the foundations, of a building.
- The laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned (above).
- Any operation in the course of laying out or constructing a road or part of a road.
- Any change in the use of any land which constitutes material development.
Ref Town and Country Planning Act 1990, Section 56.
Lawfully commencing the development works may first involve satisfying conditions applied to the permission.
If the development has not commenced within three years, the permission will be considered to have expired, and if the applicant still wishes to proceed with the development, they will need to renew the application. Renewal is generally less onerous than making a fresh application, but a fee is payable. If however, the conditions under which the original permission was granted have changed, it may be necessary to make a fresh application.
Once the development has commenced, the permission remains in place unless the local authority serves a completion notice. If such a notice is served, the development must then be completed within 12 months.
If an outline planning application has been made, then the relevant reserved matters applications must be made within three years. The permission will then last for a further 2 years.
See also: How long does it take to get planning permission.
[edit] Related articles on Designing Buildings
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Community Infrastructure Levy.
- Design and access statements.
- Detailed planning application.
- Environmental impact assessment.
- Extensions to time limits for implementing existing planning permissions.
- How long does it take to get planning permission.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- The difference between planning permission building regulations approval.
Featured articles and news
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”





















Comments